Progress report 8 September 2010

  • First sod turned by Member for South Barwon and Parliamentary Secretary for Water and Environment Michael Crutchfield, marking the start of construction works. [State Government media release]

Progress report 26 August 2010

  • Sheds and equipment have been installed on-site in preparation for the start of construction works.
  • The pre-cast concrete units that will make up much of the new ramp are currently in production in Melbourne.
  • Serious site work is scheduled to start the week commencing 6 September with the project on time for opening in October 2010.

Progress report 2 July 2010

  • The committee announces that Fitzgerald Constructions Australia has been awarded the construction contract. Read our media release.

Progress report 22 April 2010

  • State Government announces it will provide $1.2 million in funding to build the new Torquay boat ramp. Read Premier Brumby\'s media release.

 

Latest photos

\"Richard (L-R) CEO Richard Davies and local MP Michael Crutchfield turn the first sod on 8 Sept 2010.

\"Smiling The sod-turning brought smiles to everyone\'s faces as construction work got underway!

More information about this project.